Marian Vian Primary School



Chartway Construction was appointed main contractor for the internal refurbishment works of a detached former adult education building, to create a children’s nursery within the grounds of Marian Vian Primary School in Beckenham. Externally, works were required to create a nursery play area and an extension of the existing staff car park.

Additionally, there was a requirement for an external pupil drop off bay to be constructed by way of alterations to the existing school boundary and playground, along with alterations to the existing public highway and pavement.

It was imperative to the school that they must be able to continue to operate throughout the contract period during term time, therefore it was essential to plan works for minimal disruption to our client.
 

Key Project Details

Client - London Borough of Bromley
Value - £512k
Location - Beckenham
Duration - 14 weeks

This was a refurbishment project undertaken whilst the school was fully operational. It was key to establish clear lines of communication with the school in order to undertake the works to programme and with minimal disruption to the pupils and teaching staff.


Karen Alabaster-Oliver
BDM, Chartway Construction